Coming Up | History |
| |
Coming Up |
June/July 2008 |
Anticipated H.O.P. approval |
| |
Anticipated Joint Permit approval |
| |
Record Final Plan |
|
| |
History |
| Spring
2000 |
Building
Committee formed |
|
|
September 2004 |
The Upper
Leacock Twp. Board of Supervisors rezoned
approximately 53 acres of Worship Center’s
property between the stream and Route
23 |
|
|
November 2005 |
Leadership
Team met with WC family members to receive
feedback on concepts to shape
the redesign of the building plans |
|
|
February 2006 |
Leadership
Team appointed Tim Keller to lead building
team and coordinate all the details, including
design, construction, and congregational
involvement |
May 2007 |
Zoning Hearing Board decision |
January 2008 |
Received conditional approval to our preliminary land development plans from Upper Leacock supervisors |
|