Coming Up |
July 15, 2010 |
Worship receives the keys to our new facility
|
|
August 14/15, 2010 |
Last services in the current facility
|
|
August 15, 2010 |
Ribbon Cutting
|
|
August 20/21, 2010 |
First services in the new building!
|
|
October 2/3, 2010 |
Dedication Weekend
|
|
| |
History |
| Spring
2000 |
Building
Committee formed |
|
|
September 2004 |
The Upper
Leacock Twp. Board of Supervisors rezoned
approximately 53 acres of Worship Center’s
property between the stream and Route
23 |
|
|
November 2005 |
Leadership
Team met with WC family members to receive
feedback on concepts to shape
the redesign of the building plans |
|
|
February 2006 |
Leadership
Team appointed Tim Keller to lead building
team and coordinate all the details, including
design, construction, and congregational
involvement |
May 2007 |
Zoning Hearing Board decision |
January 2008 |
Received conditional approval to our preliminary land development plans from Upper Leacock supervisors |
August 2008 |
Received final approvals from Upper Leacock Twp. Board of Supervisors to proceed with our new building |
January-March 2009 |
Hearing From God – message series, small group study series, and time of fasting and praying about how each of us could be involved in the vision God has for our church. |
March 28/29, 2009 |
Celebration Weekend – Celebrating our time of Hearing From God as a church family. 3-year Giving Goal commitments for our new building were handed in and prayed over. |
April 19, 2009 |
Groundbreaking – An unforgettable night of celebration for our church family. Read more... |
May 2009 |
Sitework/construction began |
January-February 2010 |
40 days Fasting & Praying Together – A time of personal spiritual renewal and congregational consecration for the next season of ministry for Worship Center. Believing together for God's provision and receiving the new facility to be used for God's purposes. |
|