February 2006 |
Leadership
Team appointed Tim Keller to lead building
team and coordinate all the details, including
design, construction, and congregational
involvement |
May 2007 |
Zoning Hearing Board decision |
January 2008 |
Received conditional approval to our preliminary land development plans from Upper Leacock supervisors |
August 2008 |
Received final approvals from Upper Leacock Twp. Board of Supervisors to proceed with our new building |
January-March 2009 |
Hearing From God – message series, small group study series, and time of fasting and praying about how each of us could be involved in the vision God has for our church. |
March 28/29, 2009 |
Celebration Weekend – Celebrating our time of Hearing From God as a church family. 3-year Giving Goal commitments for our new building were handed in and prayed over. |
April 19, 2009 |
Groundbreaking – An unforgettable night of celebration for our church family. Read more... |
May 2009 |
Sitework/construction began |
January-February 2010 |
40 days Fasting & Praying Together – A time of personal spiritual renewal and congregational consecration for the next season of ministry for Worship Center. Believing together for God's provision and receiving the new facility to be used for God's purposes. |
July 20, 2010 |
The church staff moved their offices into the new building. Many volunteers from the church family helped make the transition a smooth one. See photos... |
August 14/15, 2010 |
Last services in former facility
|
August 15, 2010 |
Open House / Ribbon Cutting - An airplane flew overhead toting the phrase, "Worship Center - Dreams Come True" and a huge dream was truly fulfilled that day. A great celebration was had by the WC church family as we walked through this amazing gift from God. See photos... |
August 20/21, 2010 |
First services in the new building! |
October 2/3, 2010 |
The Dedication - Special guests Kenneth & Lynette Hagin joined us in celebrating what God has done as we dedicated "ourselves and our building to God." See photos... |